•Phase 1 – Q3/2022 – assembly facility start-up
•Building with 2.200 m2 for assembly with 2 assembly lines
•1.200 m2 rented building nearby for storage
•
•Phase 2 – Q4/2023
•Two buildings with 6.000 m2 (production, prototyping and storage)
•Wheel assembly in house
•
•Phase 3 – Q3/2024
•Three buildings with more than 10.000 m2 (production, prototyping and storage)